Bid Security, Performance Security and Additional Performance Security

Bid Security, Performance Security and Additional Performance Security in Standard Bidding Documents

Bid Security, Performance Security and Additional Performance Security

Understanding Financial Safeguards in Standard Bidding Documents (SBD)

Background

In the realm of government procurement and public works contracting, financial securities serve as critical protective mechanisms ensuring contractor commitment, performance reliability, and contract fulfillment. Public sector procurement involves substantial taxpayer funds, making it imperative to establish safeguards against contractor default, bid manipulation, and performance failures that could result in project delays, cost overruns, or incomplete infrastructure delivery.

Standard Bidding Documents (SBD), developed by international organizations like the World Bank, Asian Development Bank (ADB), and national procurement authorities, incorporate mandatory financial security provisions to protect the interests of procuring entities while maintaining fair competition. These documents establish uniform bidding procedures that have been adopted globally, with local adaptations reflecting regional legal frameworks and administrative practices.

Three fundamental financial securities form the backbone of procurement risk management: Bid Security (ensuring serious bidding), Performance Security (guaranteeing contract execution), and Additional Performance Security (protecting against advance payment misuse). Understanding these instruments is essential for procurement officers, contractors, civil engineers, and legal professionals involved in public sector infrastructure development.

Bid Security, Performance Security and Additional Performance Security

Understanding the Three Security Types

1
Bid Security (Earnest Money Deposit - EMD)

Definition: Bid Security, commonly known as Earnest Money Deposit (EMD), is a financial guarantee submitted by bidders along with their tender proposals to demonstrate seriousness of intent and provide compensation to the procuring entity in case the successful bidder withdraws or fails to execute the contract.

Key Characteristics:

  • Timing: Submitted with the bid documents at the tender submission stage
  • Purpose: Ensures bidders do not submit frivolous bids and commit to contract execution if selected
  • Typical Amount: 1-5% of the estimated contract value (commonly 2-3%)
  • Validity Period: Must remain valid for 28-60 days beyond the bid validity period
  • Acceptable Forms: Bank guarantee, cashier's check, demand draft, certified check, or insurance bond
  • Forfeiture Conditions: Withdrawn after opening, modification of bid terms, refusal to sign contract, failure to submit performance security
  • Return: Returned to unsuccessful bidders after contract award; returned to successful bidder after submission of performance security

⚠️ Forfeiture Scenarios

Bid security is forfeited if the bidder:

  • Withdraws the bid during the validity period
  • Refuses to accept correction of arithmetic errors in the bid
  • Fails to sign the contract agreement within the stipulated time
  • Does not furnish the required performance security within the specified period
  • Attempts to influence the evaluation process through corrupt practices
2
Performance Security (Performance Guarantee)

Definition: Performance Security is a financial guarantee provided by the successful contractor to the employer as assurance of faithful performance of all contractual obligations, including quality standards, timelines, and warranty commitments. It serves as compensation for damages and additional costs incurred if the contractor defaults or performs inadequately.

Key Characteristics:

  • Timing: Submitted within 14-28 days of contract award, before commencement of works
  • Purpose: Protects employer against contractor default, delays, defective work, and breach of contract terms
  • Typical Amount: 5-10% of the contract value (commonly 10% for construction contracts)
  • Validity Period: Entire contract duration plus defect liability period (typically 12-24 months after completion)
  • Acceptable Forms: Unconditional bank guarantee from scheduled commercial bank, insurance bond, or surety bond
  • Invocation Conditions: Contractor abandonment, poor quality work, delay penalties, breach of contract, insolvency
  • Return: Released after successful completion of defect liability period and final acceptance certificate

💡 Unconditional vs. Conditional Guarantees

Performance securities are typically unconditional and on-demand, meaning the bank pays upon first written demand from the employer without requiring proof of contractor default. This differs from conditional guarantees that necessitate legal proceedings demonstrating breach. Standard Bidding Documents mandate unconditional guarantees to enable swift remedial action.

3
Additional Performance Security (APS)

Definition: Additional Performance Security is a supplementary financial guarantee required when the employer grants advance payment to the contractor. It specifically protects the advance payment amount, ensuring recovery if the contractor fails to utilize the funds appropriately, becomes insolvent, or abandons the project before recouping the advance through work execution.

Key Characteristics:

  • Timing: Submitted before release of advance payment to the contractor
  • Purpose: Safeguards advance payment against misuse, contractor insolvency, or project abandonment
  • Typical Amount: Equal to 100% of the advance payment amount (declining security)
  • Validity Period: Until the advance is fully recovered through running bill deductions
  • Acceptable Forms: Unconditional bank guarantee or insurance bond from approved institutions
  • Declining Value: Amount reduces proportionally as advance is recovered through progressive payments
  • Return: Released when the entire advance payment has been recovered through work completion

⚠️ Advance Payment Recovery Mechanism

Advance payments are recovered by deducting a fixed percentage (typically 10-20%) from each interim payment certificate until fully recouped. The Additional Performance Security value reduces correspondingly. For example, if ₹1 crore advance is given and ₹20 lakh has been recovered, the APS should cover the remaining ₹80 lakh balance.

Comparison of Security Types

Aspect Bid Security Performance Security Additional Performance Security
Submission Stage With tender bid After contract award Before advance payment
Typical Amount 2-3% of contract 10% of contract 100% of advance
Validity Period Bid validity + 28-60 days Contract + DLP period Until advance recovered
Primary Purpose Ensure serious bidding Guarantee performance Protect advance payment
Release Condition After contract signing After DLP completion After full recovery
Nature Fixed amount Fixed amount Declining amount

Standard Bidding Documents (SBD): Overview

What are Standard Bidding Documents?

Standard Bidding Documents are internationally recognized, standardized procurement templates developed by multilateral development banks (World Bank, ADB, AfDB, EBRD) and national procurement authorities to ensure transparency, fairness, and efficiency in public procurement processes. These documents provide comprehensive frameworks covering all aspects of competitive bidding—from invitation to tender through contract execution and closure.

Key Features of SBD:

  • International Best Practices: Incorporate proven procurement methodologies refined over decades
  • Transparency and Competition: Establish clear evaluation criteria and non-discriminatory procedures
  • Legal Framework: Provide balanced contractual terms protecting both employer and contractor rights
  • Procurement Types: Separate documents for goods, works, and consulting services
  • Contract Models: Templates for various contract types (lump-sum, unit price, cost-plus)
  • Standard Clauses: Pre-drafted legal provisions covering securities, payments, variations, disputes

Common SBD Variants:

  • World Bank SBD: Most widely adopted globally, updated periodically (current version 2023)
  • ADB Standard Bidding Documents: Used extensively in Asia-Pacific region
  • FIDIC Contracts: International Federation of Consulting Engineers standard forms
  • National Adaptations: Countries customize international SBDs to reflect local laws and regulations

SBD Clauses Related to Securities

Standard Bidding Documents contain specific clauses governing the submission, format, validity, invocation, and release of financial securities. Understanding these provisions is crucial for both procuring entities and contractors.

Clause on Bid Security (ITB Clause 19 - Typical)

ITB 19.1 - Bid Security Amount

"The Bidder shall furnish as part of its bid, a Bid Security in the amount and currency specified in the BDS. The Bid Security shall be valid for 28 days beyond the validity period of the bid."

ITB 19.2 - Acceptable Forms

"The Bid Security shall be, at the Bidder's option, in any of the following forms: (a) an unconditional Bank Guarantee; (b) an irrevocable Letter of Credit; (c) a Cashier's Check, Certified Check, or Bank Draft."

ITB 19.5 - Forfeiture of Bid Security

"The Bid Security of a Bidder shall be forfeited if the Bidder: (a) withdraws its Bid during the period of bid validity; (b) does not accept the correction of errors; (c) fails to sign the Contract; or (d) fails to furnish the Performance Security."
Clause on Performance Security (GCC Clause 4 - Typical)

GCC 4.1 - Performance Security Amount

"Within twenty-eight (28) days after the receipt of the Letter of Acceptance, the Contractor shall deliver to the Employer a Performance Security in the amount and currency specified in the SCC. The Performance Security shall be issued by a bank or financial institution acceptable to the Employer."

GCC 4.2 - Unconditional Guarantee

"The Performance Security shall be denominated in the currency of the Contract, or in a freely convertible currency acceptable to the Employer, and shall be in the form of an unconditional Bank Guarantee or an irrevocable Letter of Credit issued by a reputable bank."

GCC 4.3 - Validity Period

"The Performance Security shall be valid until a date 28 days after the date of the issuance of the Certificate of Completion. The Employer shall return the Performance Security to the Contractor within 28 days following its expiry."
Clause on Advance Payment and Additional Security (GCC Clause 14 - Typical)

GCC 14.2 - Advance Payment

"The Employer shall make an advance payment to the Contractor of the amounts stated in the SCC by the date stated in the SCC, against provision by the Contractor of an Unconditional Bank Guarantee in a form and by a bank acceptable to the Employer in amounts and currencies equal to the advance payment."

GCC 14.3 - Advance Payment Security

"The Guarantee shall remain effective until the advance payment has been repaid, but the amount of the Guarantee shall be progressively reduced by the amounts repaid by the Contractor. Interest shall not be charged on the advance payment."

GCC 14.4 - Recovery of Advance

"The advance payment shall be repaid by deducting proportionate amounts from payments otherwise due to the Contractor, following the schedule of completed percentages of the Works on a payment basis. No account shall be taken of the advance payment or its repayment in assessing valuations of work done."

Practical Example: Highway Construction Project

Project Scenario

Project: Construction of 50 km National Highway
Estimated Contract Value: ₹200 Crores (₹2,000 million)
Contract Duration: 24 months
Defect Liability Period: 12 months
Advance Payment: 10% of contract value

Security Calculations:

1. Bid Security (EMD) Amount = 2% of estimated contract value
= 2% × ₹200 Crores
= ₹4 Crores (₹40 million)

Form: Bank guarantee from any scheduled commercial bank
Validity: 90 days bid validity + 28 days = 118 days from bid submission
Submission: Along with technical and financial bid documents
2. Performance Security Amount = 10% of contract value
= 10% × ₹200 Crores
= ₹20 Crores (₹200 million)

Form: Unconditional bank guarantee from scheduled commercial bank
Validity: 24 months (construction) + 12 months (DLP) + 28 days = 37 months from contract signing
Submission: Within 28 days of Letter of Acceptance, before site mobilization
3. Additional Performance Security (for Advance Payment) Advance Payment Amount = 10% of contract value
= 10% × ₹200 Crores
= ₹20 Crores

Additional Performance Security = 100% of advance payment
= 100% × ₹20 Crores
= ₹20 Crores (₹200 million)

Form: Unconditional bank guarantee (declining/reducing security)
Validity: Until full recovery of advance (estimated 18-24 months)
Submission: Before release of advance payment
Recovery: 10% deduction from each running bill until ₹20 Crores fully recovered
4. Timeline of Security Events
  • Day 0: Tender submission with ₹4 Cr bid security
  • Day 45: Bid opening and evaluation
  • Day 75: Letter of Acceptance issued to successful bidder
  • Day 80: Unsuccessful bidders' bid security (₹4 Cr each) returned
  • Day 95: Contract signed; successful bidder submits ₹20 Cr performance security
  • Day 96: Successful bidder's ₹4 Cr bid security returned
  • Day 100: Contractor submits ₹20 Cr additional performance security
  • Day 101: ₹20 Cr advance payment released to contractor
  • Month 6: First running bill certified; ₹2 Cr advance recovered; APS reduced to ₹18 Cr
  • Month 18: Full advance recovered; ₹20 Cr APS released to contractor
  • Month 24: Project completion certificate issued
  • Month 36: Defect liability period ends
  • Month 37: ₹20 Cr performance security released to contractor

💰 Total Financial Commitment by Contractor

Maximum Concurrent Securities: ₹4 Cr (bid) + ₹20 Cr (performance) + ₹20 Cr (additional) = ₹44 Crores at project commencement

Bank Charges: Typically 1-2% per annum on bank guarantee value, representing significant financial cost to contractors

Working Capital Impact: Bank guarantees require margin money (10-25% cash deposit) or collateral, affecting contractor liquidity

Practical Implications and Best Practices

For Procuring Entities (Employers)

Risk Management:

  • Verify Authenticity: Always confirm bank guarantees directly with issuing banks to prevent fraudulent submissions
  • Monitor Validity: Track guarantee expiry dates and request extensions before expiration to maintain protection
  • Timely Release: Return securities promptly upon fulfillment of conditions to maintain good contractor relationships
  • Proportionate Amounts: Set security percentages appropriate to project risk—higher for complex/critical works
  • Clear Documentation: Maintain comprehensive records of all securities received, extended, invoked, or released
  • Invocation Justification: Document clear grounds before invoking securities to defend against legal challenges

For Contractors (Bidders)

Financial Planning:

  • Banking Relationships: Maintain strong relationships with multiple banks to ensure guarantee availability
  • Margin Money Management: Plan for 10-25% cash deposits or equivalent collateral for guarantee issuance
  • Cost Inclusion: Factor bank guarantee charges (1-2% per annum) into tender pricing
  • Validity Management: Ensure guarantees have sufficient validity periods with buffer for delays
  • Performance Compliance: Adhere strictly to contract terms to avoid security forfeiture
  • Timely Submission: Submit securities within stipulated timeframes to avoid penalties or disqualification
  • Format Compliance: Use exact formats specified in SBD to avoid rejection on technicalities

Common Issues and Resolutions

Issue 1: Expired Bid Security

Problem: Evaluation process extends beyond anticipated timeline, causing bid securities to expire before contract award.

SBD Solution: Employer requests all bidders in consideration to extend bid security validity. Bidders refusing extension may be rejected. Extension requests must be reasonable and justified.

Best Practice: Initial bid security validity should include substantial buffer (60-90 days beyond estimated evaluation period).

Issue 2: Delayed Performance Security Submission

Problem: Successful bidder fails to submit performance security within the stipulated 28-day period due to banking delays or financial constraints.

SBD Provision: Employer may terminate contract and forfeit bid security. Contract awarded to second-ranked bidder if their bid remains valid.

Resolution: Contractor should request extension with valid justification before deadline. Employers may grant short extensions (7-14 days) for genuine banking delays with penalty clauses.

Issue 3: Advance Payment Recovery Disputes

Problem: Disagreements arise over the pace of advance payment recovery, affecting additional performance security reduction.

SBD Mechanism: Recovery schedule clearly defined in contract (typically proportionate to certified work completion percentage).

Best Practice: Monthly reconciliation statements showing advance balance, recovery to-date, and corresponding APS value adjustment. Bank guarantee should explicitly allow for proportionate reduction as per contract terms.

Issue 4: Fraudulent Bank Guarantees

Problem: Submission of forged or fake bank guarantees that appear genuine but are invalid.

Prevention: Mandatory direct verification with issuing bank using contact details independently sourced (not from guarantee document). Online verification portals increasingly used by banks.

Consequences: Immediate disqualification, bid security forfeiture (if applicable), blacklisting, and legal prosecution for fraud.

Recent Developments and Trends

🔄 Digital Transformation

E-Bank Guarantees: Many jurisdictions now accept electronic bank guarantees issued through bank digital platforms, reducing processing time and improving authenticity verification.

Blockchain Integration: Pilot programs exploring blockchain-based smart contracts for automatic security release upon milestone completion verification.

Central Registries: Some countries establishing central bank guarantee registries enabling instant online verification by procuring entities.

⚖️ Legal and Regulatory Updates

Reduced EMD Requirements: Some governments reducing or exempting bid security for MSMEs (Micro, Small & Medium Enterprises) to promote participation.

Performance Security Alternatives: Exploration of performance insurance bonds and surety arrangements as alternatives to traditional bank guarantees.

Faster Release Mechanisms: Regulations mandating automatic release of securities within 15-30 days of entitlement to reduce contractor working capital blockage.

Invocation Restrictions: Courts increasingly scrutinizing arbitrary security invocations, requiring employers to demonstrate clear breach before encashment.

Key Differences Across International SBDs

Aspect World Bank SBD ADB SBD FIDIC Contracts
Bid Security Typically 2-5% Typically 2% Per tender documents
Performance Security 10% standard 10% standard 5-10% (per SCC)
Advance Payment Up to 20% Up to 15% Varies by contract
APS Amount 100% of advance 100% of advance 100% of advance
Release Timeline 28 days post-DLP 56 days post-DLP Per contract terms

Conclusion

Bid Security, Performance Security, and Additional Performance Security constitute fundamental pillars of public procurement risk management, providing essential safeguards that protect taxpayer investments while maintaining contractor accountability throughout the project lifecycle. These financial instruments, meticulously codified in Standard Bidding Documents developed by international development institutions, create a balanced framework that deters frivolous bidding, ensures contract fulfillment, and protects advance payments against misuse.

Understanding the distinct purposes, timing requirements, and regulatory provisions governing each security type is imperative for all stakeholders in public works contracting. Procuring entities must implement robust verification procedures, monitor validity periods vigilantly, and exercise invocation powers judiciously to maintain both project protection and contractor trust. Contractors, conversely, must plan financial resources adequately, maintain strong banking relationships, and comply meticulously with security submission requirements to avoid disqualification or forfeiture.

The evolution of procurement practices—embracing digital guarantees, exploring alternative surety mechanisms, and streamlining release processes—promises enhanced efficiency while preserving the core protective functions these securities serve. As infrastructure demands escalate globally, the standardized security frameworks embedded in SBDs will continue providing the foundational trust infrastructure enabling billions of dollars in public works delivery annually.

Ultimately, these seemingly bureaucratic financial instruments represent far more than procedural formalities—they embody the contractual commitment, financial capacity verification, and performance assurance essential to transforming public procurement from mere paper agreements into tangible infrastructure that serves communities for generations. Mastery of security provisions, therefore, constitutes not peripheral knowledge but core competency for professionals dedicated to excellence in public infrastructure development.

📚 Further Reading & References

  • World Bank Standard Bidding Documents (Latest Edition 2023)
  • Asian Development Bank Procurement Guidelines
  • FIDIC Conditions of Contract (Red Book, Yellow Book)
  • National Procurement Regulations of respective countries
  • General Financial Rules (GFR) - Government of India
  • Manual for Procurement of Works - Central Public Works Department

Disclaimer

This article provides general information on bid security, performance security, and additional performance security provisions in Standard Bidding Documents. Specific requirements may vary by jurisdiction, funding agency, and project type. Always refer to the actual SBD and applicable local regulations for authoritative guidance. This content is for educational purposes and does not constitute legal or financial advice.