Detailed Rate Analysis – M25 RMC Pumped Concrete

Detailed Rate Analysis – M25 RMC Pumped Concrete

Detailed Rate Analysis – M25 RMC Pumped Concrete (Extra Item)

Basis: M25 Design Mix RMC, 25 km lead, 20 m pumping height, Indian standard practice (2024–25)

Sr. No. Particular Description No. Quantity Unit Rate (₹) Amount (₹) Remarks
1 M25 Concreting (RMC) Providing and placing M25 grade ready mix concrete, machine mixed, pumped, laid, compacted, finished, cured including shuttering and scaffolding complete. — 1 m³ — — Main item
1.1 Material Cement (OPC/PPC ~400 kg) — 0.40 MT 9,500 3,800 As per design mix
1.2 Material Fine aggregate (Manufactured sand) — 0.45 m³ 1,200 540 Zone-II
1.3 Material Coarse aggregate (20mm & 10mm) — 0.85 m³ 1,100 935 Machine crushed
1.4 Material Admixture & water L.S. — — 225 225 Plasticizer
Sub-Total – Materials 5,500
2 Manpower Labour for placing, finishing & curing — — — — —
2.1 Skilled labour Mason / operator assistance 1 1 Day 800 800
2.2 Unskilled labour Helpers, curing, cleaning 2 1 Day 450 900
Sub-Total – Labour 1,700
3 Machinery Construction equipment — — — — —
3.1 Concrete pump Including pipeline (20 m head) — 1 m³ 300 300
3.2 Needle vibrator Operation & fuel L.S. — — 100 100
Sub-Total – Machinery 400
4 Transportation Transit mixer – 25 km lead — 1 m³ 225 225
5 Sundries Line losses, tools, safety, cleaning L.S. — — 100 100
6 Testing Cube test, slump test, documentation L.S. — — 50 50 IS 456
Total (Before Statutory Charges) 8,075
7 Labour Cess 1% BOCW Act — — — — 81 Statutory
8 GST 18% on works contract — — — — 1,468 As applicable
GRAND TOTAL RATE ₹ 9,624 / m³ Final payable
Related Civil Engineering Articles
Loading...
Notes:
• Rates are indicative and shall be governed by SSR/DSR & contract clauses
• GST and Labour Cess are mandatory statutory payments
• Overheads & profit deemed included in analysis
• Suitable for Extra Item / Revised Estimate / Final Bill justification

Post a Comment

Previous Post Next Post